Construction Product Availability: 24th August 2021

August 25, 2021

Statement from John Newcomb, CEO of the Builders Merchants Federation and Peter Caplehorn, CEO of the Construction Products Association, co-chairs of the Construction Leadership Council’s Product Availability working group


Although the overall supply situation has not changed substantially, there has been a temporary easing this month, most probably due to a combination of the holiday period and some domestic customers delaying or cancelling projects due to higher costs or cost uncertainty.

Timber, cement, roofing products, bricks, blocks, insulation and steel remain the products in shortest supply.  Although product and material price inflation has slowed, most predict it will be 2022 before prices stabilise.  

However, haulage, and the lack of availability of drivers, is now the major concern affecting distribution with some suppliers asking builders merchants to collect their orders as they cannot get enough drivers to sustain deliveries.

Regional distribution is a particular issue, with challenges arranging deliveries to Scotland and the South West of England. The problem is not limited to our sector, and with similar haulage issues affecting a wider distribution network there is no short-term fix.  The Department for Transport is engaging with the freight sector and hauliers to look at both interim and longer-term solutions, which require collaboration between government and the sector.

Container shipping continues to affect imports.  Key ports in China are closed due to Covid, but the backlog extends beyond China throughout distribution centres worldwide.  This is forecast to continue through the peak Christmas season into early 2022. With capacity at a premium, container prices remain high. However, these rates are not sustainable in the long term and when demand signals change, we are likely to see prices reduce.

Looking forward, the group discussed the requirement for aggregates and other key products when HS2 demand reaches its  peak in 2022/23. Projected volumes are being shared with industry trade bodies, key suppliers and the CLC Product Availability Group to ensure there is sufficient capacity in the market to deliver HS2 as well as all other projects.  This is a particular concern for smaller builders, who may require their own allocation.

Manufacturers and trade associations are providing updates on their own areas, including:

Timber Trade Federation

« Read more news

Read PlumbHeat

Not a member? Enter your details below for a sneak peek of our latest issue of our quarterly magazine.
Cover of theAutumn Issue issue
Cover of theSummer 2021 issue
Cover of theSpring 2021 issue